The firearm certificate register has missed another key deadline

More delays arrest police intelligence sharing plan

One data sharing project cancelled, another slips even further behind schedule

Written by Emma Nash and Sarah Arnott

Plans for a national police intelligence scheme are being plagued by further problems, with the scrapping of one key project and yet more delays to another.

The Cross Regional Information Sharing Project (Crisp) – an interim stage of the Impact programme created following the Bichard Inquiry into the Soham murders – is being cancelled, Home Office minister Tony McNulty told Parliament on Tuesday.

And 10 years after it became a legal requirement, the national firearm certificate register has missed another key deadline and will now not be fully operational until the end of August.

The creation of a national database of certificate holders linked to the Police National Computer (PNC) was passed into law in 1997, following the 1996 Dunblane massacre, but its development has been beset with difficulties.

Now the National Policing Improvement Agency (NPIA), which runs the project, says problems with data cleansing within individual forces mean the National Firearms Licensing Management System (NFLMS) will not meet its most recently revised deadline of linking with the PNC by June.

‘Forces that have only recently installed the system will not have time to cleanse their data,’ said an NPIA spokeswoman.

But some forces are still struggling to get the system operational. The NPIA says 90 per cent of forces are successfully running NFLMS, but others have local technology problems.

South Wales Police has sent a letter to firearm certificate holders informing them that ‘administrative difficulties’ are causing delays in issuing certificates.

The letter says: ‘Applications received and accepted before the expiry date will deem that you remain the holder of a certificate even though administrative difficulties may delay sending a new certificate to you.’

Labour peer Lord Corbett of Castle Vale is calling for the National Audit Office to hold an inquiry into the project.

‘This is a sad saga of technical incompetence alongside what seems to be an orchestrated attempt to ensure that the NFLMS is never properly operational,’ he said.

The NFLMS is part of the Impact national information sharing programme, along with seven other systems including crime, child abuse and domestic violence.

Crisp is an interim step to the capability described by Sir Michael Bichard as ‘a national priority’ in June 2004.

Its demise will delay forces’ access to intelligence held by colleagues in other areas until Impact’s Police National Database starts in 2010.

reader comments

related articles

Picture of police officers

Budget threat to police plans

Cutbacks could force a rewrite of national database scheme for sharing intelligence information 08 Mar 2007

 

Date finally agreed for firearms register

Pilots begin this month with full rollout by March 01 Jun 2006

Police signal shift in strategy

New police agency turns focus to creation of common standards 05 Apr 2007

Doubts linger over police IT

Widespread support may not be enough for ambitious national plan 28 Sep 2006

Police radio backup falls short

Airwave fails to meet government’s own resilience guidelines 23 Nov 2006

Police data sharing progresses

Second phase of Crisp project set to be in place by next summer 21 Sep 2006

Blair admits to police IT complexity

Prime Minister describes Impact project as 'difficult and complicated’ 22 Jun 2006

Bichard recommendations not yet implemented fully

Police still not sharing information properly as system costs rocket 17 Jul 2008

Police single sign-on delayed

Forces face up to a two-year wait for unified access to national systems 17 Apr 2008

DNA database 'criminalises' the innocent

Government inquiry demands removal of one million DNA records from national database 31 Jul 2008

related whitepapers

today's top stories

Coding moves with the times

We examine how software development has evolved to better serve the changing needs of business, and speaks to IT leaders who are delivering significant benefits to their organisations by using the latest programming methods 15 Oct 2008

Agile framework simplifies offshore development

Case study: Getronics business application services 15 Oct 2008

Computing launches all-new IT jobs site

Updated Computingcareers.co.uk provides enhanced feature for jobseekers 14 Oct 2008

Q&A: BT Business head of SaaS, Chris Lindsay

BT's head of software-as-a-service explains the benefits of the on-demand delivery model and how the current economic downturn could force firms to re-evaluate how they buy software 14 Oct 2008

WiMax: Threat or opportunity?

We examine the merits of WiMax and its benefits relative to other wireless technologies in our latest video 13 Oct 2008

Advertisement

Newsletter signup

Sign up for our range of FREE newsletters:

Existing User

Newsletter user login:

Jobs

Related jobs

Job of the week

Job alerts

Sign up here

Find your next job

IT Salary Checker

Check salary here

Advertisement

White papers

Search white papers

Top categories

VPN, Extranet and Intranet Solutions

WAN/ LAN Solutions

Network Security

Interoperability-Connectivity

Grid/ Utility Computing

Latest poll

Are you worried about your job prospects in IT over the next 12 months?

Are you worried about your job prospects in IT over the next 12 months?

Will the economic crisis affect your job prospects?

Previous poll results

Latest audio and video articles

Remote workerVideo

WiMax: Threat or opportunity?

We examine the merits of WiMax and its benefits relative to other wireless technologies in our latest video 13 Oct 2008

programming codeVideo

The definitive guide to software development

Five key trends and five best practice tips to help you improve your programming capabilities 09 Oct 2008

Latest in-depth articles

Features

Enter the dragons' den

Getting an innovative IT product off the ground takes cash, commitment and a lot of patience 15 Oct 2008

TimepieceFeatures

Coding moves with the times

We examine how software development has evolved to better serve the changing needs of business, and speaks to IT leaders who are delivering significant benefits to their organisations by using the latest programming methods 15 Oct 2008

Advertisement

Primary Navigation